[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136869":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136869,797,2,"多选题","架空线路竣工验收检查的内容有（）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","杆塔是否直立",true,{"key":16,"text":17,"correct":18},"B","在阴天实测电阻，不得超过规定值",false,{"key":20,"text":21,"correct":14},"C","拉线是否紧固",{"key":23,"text":24,"correct":14},"D","拉线坑、杆塔坑是否符合填土要求",{"key":26,"text":27,"correct":14},"E","杆塔全高误差值是否符合原设计要求","ACDE","2020版教材P86 \u002F 2019版教材P75 （七）竣工验收检查1.杆塔直立，横担与线路中心垂直;2.杆塔全高误差值及杆塔根基误差值符合设计要求;3.拉线紧固，受力情况平衡;4.拉线坑、杆塔坑符合填土要求;5.检查弧垂、绝缘子串倾斜，跳线对各部的电气距离是否达到设计要求;6.线路导线电阻不超过规定值;7.线路的绝缘电阻符合标准要求;8.额定电压下对空载线路冲击合闸3次，无问题。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]