[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136832,797,2,"多选题","消防工程验收程序通常为（）等阶段。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","验收受理",true,{"key":16,"text":17,"correct":14},"B","工程移交",{"key":19,"text":20,"correct":14},"C","现场检查",{"key":22,"text":23,"correct":14},"D","结论评定",{"key":25,"text":26,"correct":27},"E","现场分析",false,"ABCD","2020版教材P237 \u002F 2019版教材P224 2.消防工程验收程序：验收程序通常为验收受理、现场检查、现场验收、结论评定和工程移交等阶段。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]