[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136779":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136779,797,2,"多选题","建筑电气工程中，金属槽盒安装的要求有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","配线槽盒宜安装在冷水管的下方",false,{"key":16,"text":17,"correct":18},"B","配线槽盒应敷设在热水管的下方",true,{"key":20,"text":21,"correct":18},"C","穿越防火区的槽盒应有防火措施",{"key":23,"text":24,"correct":14},"D","60m槽盒有2处与保护导体连接",{"key":26,"text":27,"correct":18},"E","起始端和终点端均应可靠地接地","BCE","2020版教材P180 \u002F 2019版教材P169 槽盒安装要求： （1）配线槽盒与水管同侧上下敷设时，宜安装在水管的上方；与热水管、蒸汽管平行上下敷设时，应敷设在热水管、蒸汽管的下方；相互间的最小距离宜符合《建筑电气工程施工质量验收规范》GB50303-2015的规定。 （2）敷设在电气竖井内穿楼板处和穿越不同防火区的槽盒，应有防火隔墙措施。 （3）槽盒全长不大于30m时，不应少于2处与保护导体可靠连接；全长大于30m时，每隔20~30m应增加一个接地连接点，起始端和终点端均应可靠地接地。 (4)敷设在电气竖井内的电缆梯架或托盘，其固定支架不应安装在固定电缆的横担上，且每隔3~5层应设置承重支架。 (5)对于敷设在室外的梯架、托盘和槽盒，当进入室内或配电箱(柜)时应有防雨水措施，槽盒底部应有泄水孔。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]