[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136777":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136777,797,2,"多选题","下列工序中，属于动力设备施工工序的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","配电箱安装",false,{"key":16,"text":17,"correct":18},"B","电动机检查",true,{"key":20,"text":21,"correct":18},"C","控制设备安装",{"key":23,"text":24,"correct":18},"D","电动机接线",{"key":26,"text":27,"correct":18},"E","送电前的检查","BCDE","2020版教材P178 \u002F 2019版教材P167 2.动力设备施工程序。设备开箱检查→设备安装→电动机检查、接线→电机干燥→（受潮时）→控制设备安装→送电前的检查→送电运行。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]