[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136776":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136776,797,2,"多选题","关于照明系统的测试和通电试运行的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","导线绝缘电阻测试应在导线接续前完成",true,{"key":16,"text":17,"correct":14},"B","灯具的绝缘电阻测试应在器具就位前完成",{"key":19,"text":20,"correct":21},"C","照明配电箱绝缘电阻测试应在接线后完成",false,{"key":23,"text":24,"correct":14},"D","照明回路剩余电流动作保护器应检测合格",{"key":26,"text":27,"correct":21},"E","应急照明电源做自动投切试验应卸除负荷","ABD","2020版教材P186 \u002F 2019版教材P175 10.照明系统的测试和通电试运行 （1）导线绝缘电阻测试应在导线接续前完成。（2）照明配电箱、灯具、开关和插座的绝缘电阻测试应在器具就位前或接线前完成。（3）照明回路装有剩余电流动作保护器时，剩余电流动作保护器应检测合格。（4）备用照明电源或应急照明电源做空载自动投切试验前，应卸除负荷，有载自动投切试验应在空载自动投切试验合格后进行。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]