[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136768":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136768,797,2,"多选题","在不赶工的前提下，高层住宅给水排水及室内雨落管道应在（ ）后，再穿外墙做出户管道。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","结构封顶",true,{"key":16,"text":17,"correct":14},"B","初沉降",{"key":19,"text":20,"correct":21},"C","室内管道安装",false,{"key":23,"text":24,"correct":21},"D","室内管道试压",{"key":26,"text":27,"correct":21},"E","室内管道防腐施工","AB","2020版教材P176 \u002F 2019版教材P165 建筑管道施工应注意的问题 高层住宅因高度大，层数多，沉降量大，安装给水排水及室内雨水落管道时，要避免出地下室的管道承受沉降的剪力而损坏。应在结构封顶并经初沉后进行施工，如果因赶工需要同步进行安装，则应先安装建筑物内的管道，等结构封顶初沉后再穿外墙做出户管道。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]