[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136754":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136754,797,2,"多选题","预防焊接变形的装配工艺措施（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合理的焊接线能量",false,{"key":16,"text":17,"correct":18},"B","预留收缩余量",true,{"key":20,"text":21,"correct":14},"C","合理安排焊缝位置",{"key":23,"text":24,"correct":18},"D","合理选择装配程序",{"key":26,"text":27,"correct":18},"E","刚性固定","BDE","2020版教材P64 \u002F 2019版教材P53 2.采取合理的装配工艺措施。（1）预留收缩余量法。（2）反变形法。（3）刚性固定法。（4）合理选择装配程序。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]