[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136743":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136743,797,2,"多选题","降低焊接应力的工艺措施，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用较大的焊接线能量",false,{"key":16,"text":17,"correct":18},"B","合理安排装配焊接顺序",true,{"key":20,"text":21,"correct":18},"C","层间进行锤击",{"key":23,"text":24,"correct":18},"D","预热拉伸补偿焊缝收缩",{"key":26,"text":27,"correct":18},"E","消氢处理","BCDE","2020版教材P62 \u002F 2019版教材P52 2.工艺措施 （1）采用较小的焊接线能量。（2）合理安排装配焊接顺序。（3）层间进行锤击。（4）预热拉伸补偿焊缝收缩（机械拉伸或加热拉伸）。（5）焊接高强钢时，选用塑性较好的焊条。（6）预热。（7）消氢处理。（8）焊后热处理。（9）利用振动法来消除焊接残余应力。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]