[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136733":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136733,797,2,"多选题","吊装载荷包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","吊车臂重",false,{"key":16,"text":17,"correct":18},"B","设备重量",true,{"key":20,"text":21,"correct":18},"C","起重索具重量",{"key":23,"text":24,"correct":18},"D","吊具重量",{"key":26,"text":27,"correct":14},"E","载荷系数","BCD","P42 吊装载荷指设备、吊钩组件、吊索（吊钩以上滑轮组间钢丝绳质量）、吊具及其他附件等的质量总和。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]