[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136730":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136730,797,2,"多选题","吊装方案的主要内容包括（）等。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制依据",true,{"key":16,"text":17,"correct":14},"B","安全保证体系及措施",{"key":19,"text":20,"correct":14},"C","工艺设计",{"key":22,"text":23,"correct":14},"D","质量保证体系及措施",{"key":25,"text":26,"correct":27},"E","成本分析与降低成本措施",false,"ABCD","2020版教材P50 \u002F 2019版教材P40 吊装方案的主要内容：（1）编制说明与编制依据；（2）工程概况；（3）吊装工艺设计；（4）吊装组织体系；（5）安全保证体系及措施；（6）质量保证体系及措施；（7）吊装应急预案；（8）吊装计算校核书。 成本分析属于吊装方法的基本选择步骤~",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]