[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136699":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136699,797,2,"多选题","设备基础施工的测量工作大体包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设备基础位置的确认",true,{"key":16,"text":17,"correct":18},"B","进行基础定位",false,{"key":20,"text":21,"correct":14},"C","标高基准点的确立",{"key":23,"text":24,"correct":14},"D","设备基础标高测量",{"key":26,"text":27,"correct":18},"E","设备安装","ACD","2020版教材P36 \u002F 2019版教材P27 设备基础的测量工作大体包括以下步骤，设备基础位置的确认，设备基础放线，标高基准点的确立，设备基础标高测量。",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]