[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136697":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1136697,797,2,"多选题","设备基础施工的测量工作一般包括的步骤有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设备基础位置的确认",true,{"key":16,"text":17,"correct":14},"B","设备基础放线",{"key":19,"text":20,"correct":14},"C","标高基准点的确立",{"key":22,"text":23,"correct":24},"D","基础沉降观测测量",false,{"key":26,"text":27,"correct":14},"E","设备基础标高测量","ABCE","2020版教材P36 \u002F 2019版教材P27 大体包括以下步骤，设备基础位置的确认，设备基础放线，标高基准点的确立，设备基础标高测量",{"id":6,"name":31,"category":32,"favorite":33},"一建机电工程实务","建筑工程",0]