[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136649,797,1,"单选题","（2019年真题）临时用电组织设计的主要内容不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电费的计算方式",true,{"key":16,"text":17,"correct":18},"B","电源的接线位置",false,{"key":20,"text":21,"correct":18},"C","配电箱的安装位置",{"key":23,"text":24,"correct":18},"D","电路接线系统图","临时用电施工组织设计主要内容应包括：现场勘察；确定电源进线、变电所、配电室、总配电箱、 分配电箱等的位置及线路走向；进行负荷计算；选择变压器容量、导线截面积和电器的类型、规格；绘制 电气平面图、立面图和接线系统图；配电装置安装、防雷接地安装、线路敷设等施工内容的技术要求；建 立用电施工管理组织机构；制定安全用电技术措施和电气防火措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]