[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136628,797,1,"单选题","（2016年真题）工业安装分项工程质量验收时，验收成员不包括（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位专业技术负责人",false,{"key":16,"text":17,"correct":18},"B","设计单位驻现场代表",true,{"key":20,"text":21,"correct":14},"C","施工单位专业技术质量负责人",{"key":23,"text":24,"correct":14},"D","监理工程师","分项工程质量验收记录应由施工单位质量检验员填写，验收结论由建设（监理）单位填写。填 写的主要内容：检验项目；施工单位检验结果；建设（监理）单位验收结论。结论为“合格”或“不合格”。 记录表签字人为施工单位专业技术质量负责人；建设单位专业技术负责人；监理工程师。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]