[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136617,797,1,"单选题","（2019年真题）施工阶段项目成本控制要点包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","落实成本计划",true,{"key":16,"text":17,"correct":18},"B","成本预测",false,{"key":20,"text":21,"correct":18},"C","成本计划分解",{"key":23,"text":24,"correct":18},"D","成本考核","施工阶段项目成本的控制要点 （1）对分解的成本计划进行落实。 （2）记录、整理、核算实际发生的费用，计算实际成本。 （3）进行成本差异分析，采取有效的纠偏措施，充分注意不利差异产生的原因，以防对后续作业成本产 生不利影响或因质量低劣而造成返工现象。 （4）注意工程变更，关注不可预计的外部条件对成本控制的影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]