[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136603,797,1,"单选题","（2016年真题）耐火喷涂料喷涂完毕后，应及时（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","作防水处理",false,{"key":16,"text":17,"correct":14},"B","进行烘干",{"key":19,"text":20,"correct":21},"C","开设膨胀缝",true,{"key":23,"text":24,"correct":14},"D","敲击释放应力","耐火喷涂料施工的主要技术要求 1.喷涂料应采用半干法喷涂，喷涂料加人喷涂机之前，应适当加水润湿，并搅拌均匀； 2.喷涂时，料和水应均匀连续喷射，喷涂面上不允许出现干料或流淌； 3.喷涂方向应垂直于受喷面，喷嘴与喷涂面的距离宜为 1~1.5m，喷嘴应不断地进行螺旋式移动，使粗细颗粒分布均匀； 4.喷涂应分段连续进行，一次喷到设计厚度，内衬较厚需分层喷涂时，应在前层喷涂料凝结前喷完次层； 5.施工中断时，宜将接槎处做成直槎，继续喷涂前应用水润湿； 6.喷涂完毕后，应及时开设膨胀缝线，可用 1~3mm 厚的模形板压人 30~50mm 而成",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]