[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136591,797,1,"单选题","（2020年真题）下列自动化仪表工程的试验内容中，必须全数检验的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单台仪表校准和试验",false,{"key":16,"text":17,"correct":14},"B","仪表电源设备的试验",{"key":19,"text":20,"correct":14},"C","综合控制系统的试验",{"key":22,"text":23,"correct":24},"D","回路试验和系统试验",true,"P142-145 综合控制系统可先在控制室内以与就地线路项链的输入输出端为界进行回路试验，再与现场仪表连接进行整个回路的试验",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]