[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136577,797,1,"单选题","（2012年真题）某台分馏塔共分为三段，采用由下至上逐段组对安装的方法，其第三段（上段）吊装、找正的紧前工序 是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第一、二段段间环焊缝组对焊接",true,{"key":16,"text":17,"correct":18},"B","第二段找正",false,{"key":20,"text":21,"correct":18},"C","第二、三段段间环焊缝组对焊接",{"key":23,"text":24,"correct":18},"D","紧固地脚螺栓","本题考查的是塔器设备的安装技术。在基础由下至上逐段组对安装程序：基础验收、设置垫铁→ 塔器的最下段（带裙座段）吊装就位、找正→吊装第二段（由下至上排序）、找正→组焊段间环焊缝、无 损检测→逐段吊装直至吊装最上段（带顶封头段）、找正→组焊段间环焊缝、无损检测→整体找正、紧固 地脚螺栓、垫铁点固及二次灌浆",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]