[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136575,797,1,"单选题","（2018年真题）立式圆筒形钢制储罐底板在不同阶段的施焊顺序，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先壁板与边缘板角焊缝，再边缘板剩余对接焊缝",true,{"key":16,"text":17,"correct":18},"B","先中幅板间长焊缝，再中幅板间短焊缝",false,{"key":20,"text":21,"correct":18},"C","先中幅板与边缘板环焊缝，再中幅板间焊缝",{"key":23,"text":24,"correct":18},"D","先中幅板间焊缝，再边缘板对接焊缝","罐底焊接工艺 焊接顺序：中幅板焊缝→罐底边缘板对接焊缝靠边缘的 300mm 部位→罐底与罐壁板连接的角焊缝（在底圈 壁板纵焊缝焊完后施焊）→边缘板剩余对接焊缝→边缘板与中幅板之间的收缩缝。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]