[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136569,797,1,"单选题","（2017年真题）管道系统压力试验前，应具备的条件是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道上的膨胀节己设置临时约束装置",true,{"key":16,"text":17,"correct":18},"B","管道焊缝己防腐绝热",false,{"key":20,"text":21,"correct":18},"C","试验压力表不少于 1 块",{"key":23,"text":24,"correct":18},"D","管道上的安全阀处于自然状态","工业管道管道压力试验前应具备的条件： （1）管道上的膨胀节己设置了临时约束装置，A 正确 （2）试验范围内的管道安装工程除涂漆、绝热外，已按设计图纸全部完成，安装质量符合有关规定，B 错 误（3）试验用压力表在周检期内并已经校验，其精度不得低于 1.6 级，表的满刻度值应为被测最大压力的 1.5-2 倍，压力表不得少于两块。C 错误 （4）待试管道上的安全阀、爆破片及仪表元件等己拆下或加以隔离，D 错误",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]