[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136563,797,1,"单选题","（2020年真题）发电机安装程序中，发电机穿转子的紧后工序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","端盖及轴承调整安装",false,{"key":16,"text":17,"correct":18},"B","氢冷器安装",true,{"key":20,"text":21,"correct":14},"C","定子及转子水压试验",{"key":23,"text":24,"correct":14},"D","励磁机安装","P123-128 发电机设备的安装程序是：定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装→端盖，轴承，密封瓦调整安装→励磁机安装→对轮复找中心并连接→整体气密性试验等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]