[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136535,797,1,"单选题","（2012年真题）室内卫生间埋地排水管道隐蔽前施工单位必须做（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压力试验",false,{"key":16,"text":17,"correct":18},"B","灌水试验",true,{"key":20,"text":21,"correct":14},"C","通球试验",{"key":23,"text":24,"correct":14},"D","稳定性试验","本题考查的是建筑管道施工技术要点。室内隐蔽或埋地的排水管道在隐蔽前必须做灌水试验",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]