[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136534,797,1,"单选题","（2013年真题）采暖管道冲洗完毕后，应（ ）、加热，进行试运行和调试。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试压",false,{"key":16,"text":17,"correct":18},"B","通水",true,{"key":20,"text":21,"correct":14},"C","通球",{"key":23,"text":24,"correct":14},"D","灌水","本题考查的是建筑管道工程施工程序。采暖管道冲洗完毕后应通水、加热，进行试运行与调试。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]