[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136494,797,1,"单选题","检验批质量验收合格的规定中不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主控项目质量经抽样检验合格",false,{"key":16,"text":17,"correct":14},"B","施工操作依据和质量验收记录完整",{"key":19,"text":20,"correct":14},"C","一般项目质量经抽样检验合格",{"key":22,"text":23,"correct":24},"D","观感质量应符合要求",true,"检验批质量验收合格标准： （1）主控项目的质量经抽样检验均应合格、一般项目的质量经抽样检验合格； （2）具有完整的施工操作依据、质量验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]