[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136462,797,1,"单选题","下列关于施工进度偏差分析，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","若出现偏差的工作为关键工作，则无论偏差大小，都对后续工作及总工期产生影响",false,{"key":16,"text":17,"correct":18},"B","若出现偏差的工作不是关键工作，对后续工期无影响",true,{"key":20,"text":21,"correct":14},"C","若出现偏差的工作不是关键工作，对后续工期可能有影响",{"key":23,"text":24,"correct":14},"D","若出现偏差的工作不是关键工作，需要根据偏差值与总时差大小关系，确定对总工期的影响程度","若出现偏差的工作不是关键工作，对后续工期的影响，还需看偏差和该工作的总时差之间的大小关系。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]