[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136461":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136461,797,1,"单选题","不属于施工进度偏差产生的主要原因是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","供应商违约",false,{"key":16,"text":17,"correct":14},"B","施工图纸修改",{"key":19,"text":20,"correct":14},"C","施工方法错误",{"key":22,"text":23,"correct":24},"D","施工质量检验",true,"施工进度偏差产生的原因 （1）设计单位原因：施工图纸提供不及时或图纸修改； （2）建设单位原因：建设资金没有落实，工程款不能按时交付。 （3）施工单位原因：项目管理混乱，施工计划编制失误，分包单位违约，施工现场协调不好，施工人员偏少，施工方案、施工方法不当等。 （4）供应商原因：供应商违约或检验后不合格。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]