[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136453":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136453,797,1,"单选题","设备采购文件的编制依据中不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目合同",false,{"key":16,"text":17,"correct":14},"B","采购计划",{"key":19,"text":20,"correct":21},"C","设计说明",true,{"key":23,"text":24,"correct":14},"D","业主要求","设备采购文件编制依据有：工程项目建设合同、设备请购书、采购计划及业主方对设备采购的相关规定等文件",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]