[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136451,797,1,"单选题","下列情况中，可向建设单位提出费用索赔的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理单位责令剥离检查未报检的隐蔽工程而产生的费用",false,{"key":16,"text":17,"correct":14},"B","施工单位的设备被暴雨淋湿而产生的费用",{"key":19,"text":20,"correct":21},"C","建设单位增加工作量造成的费用增加",true,{"key":23,"text":24,"correct":14},"D","施工单位施工人员高处坠落受伤产生的费用","索赔成立的前提条件，应同时具备以下三个前提条件： （1）与合同对照，事件已造成了承包人工程项目成本的额外支出，或直接工期损失。 （2）造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任。 （3）承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]