[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136449,797,1,"单选题","合同实施偏差分析不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","产生偏差的原因分析",false,{"key":16,"text":17,"correct":14},"B","合同实施偏差的责任分析",{"key":19,"text":20,"correct":14},"C","合同实施趋势分析",{"key":22,"text":23,"correct":24},"D","合同实施措施分析",true,"合同实施的偏差分析内容包括：产生偏差的原因分析；合同实施偏差的责任分析；合同实施趋势分析。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]