[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136443,797,1,"单选题","砌筑拱和拱顶时，必须（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从一侧拱脚开始，依次砌向另一侧拱脚",false,{"key":16,"text":17,"correct":14},"B","从顶部中心开始，同步向两侧拱脚处砌筑",{"key":19,"text":20,"correct":21},"C","从两侧拱脚开始，同时向顶部中心对称砌筑",true,{"key":23,"text":24,"correct":14},"D","从一侧拱脚向顶部中心砌筑到位后，再从另一侧拱脚向顶部中心砌筑","拱和拱顶砌筑的技术要求： （1）拱和拱顶必须从两侧拱脚同时向中心对称砌筑。 （2）锁砖应按拱合拱顶的中心线对称均匀分布。两侧对称的锁砖应同时均匀打入。不得使用砍掉厚度1\u002F3以上的锁砖。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]