[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136437":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136437,797,1,"单选题","下列关于绝热层施工的技术要求，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","保温层厚度大于等于80mm时，应分层施工",false,{"key":16,"text":17,"correct":14},"B","硬质绝热制品用作保温层时，拼缝宽度应小于等于6mm",{"key":19,"text":20,"correct":14},"C","水平管道的纵向接缝位置，不得布置在管道上部垂直中心线45°范围内",{"key":22,"text":23,"correct":24},"D","每层及层间接缝应错开，其搭接长度宜大于等于100mm",true,"绝热层施工一般规定： （1）保温层厚度≥100mm或保冷层厚度≥ 80mm吋，应分层施工。 （2）硬质或半硬质绝热制品拼缝宽度保温层≤5mm、保冷层≤2mm （3）每层及层间接缝应错开，其搭接的长度宜≥100mm。 （4）水平管道的纵向接缝，不得布置在其下部垂直中心线45°范围内。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]