[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136415,797,1,"单选题","电站锅炉钢结构质量控制中，不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安装前应确认高强度螺栓连接点安装方法",false,{"key":16,"text":17,"correct":14},"B","每层构架安装后，检查柱垂直度、大梁标高",{"key":19,"text":20,"correct":14},"C","钢结构安装后，复测柱垂直度、大梁标高",{"key":22,"text":23,"correct":24},"D","按比例抽检高强度螺栓连接点终紧质量",true,"锅炉钢结构安装质量控制 安装前应确认高强螺栓连接点安装方法，临时螺栓、定位销数量符合规程要求。每层构架安装结束后检查柱垂直度、大梁标高并作记录，对高强螺栓连接质量按规程全面检查确认合格。钢结构安装后按规程复测、柱垂直度、大梁标高合格验收记录，检查所有高强螺栓连接点终紧质量。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]