[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136412,797,1,"单选题","光伏发电设备安装时，汇流箱安装的紧后工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","光伏组件安装",false,{"key":16,"text":17,"correct":14},"B","电气设备安装",{"key":19,"text":20,"correct":14},"C","光伏支架安装",{"key":22,"text":23,"correct":24},"D","逆变器安装",true,"汇流箱安装→逆变器安装",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]