[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136411,797,1,"单选题","发电机设备的安装程序中，发电机穿转子的紧前工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定子就位",false,{"key":16,"text":17,"correct":18},"B","定子及转子水压试验",true,{"key":20,"text":21,"correct":14},"C","氢冷器安装",{"key":23,"text":24,"correct":14},"D","端盖、轴承、密封瓦调整安装","定子及转子水压试验→发电机穿转子",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]