[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136377,797,1,"单选题","大型储罐的管道与泵或其他有独立基础的设备连接，应注意基础（ ）的影响。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","沉降",true,{"key":16,"text":17,"correct":18},"B","位移",false,{"key":20,"text":21,"correct":18},"C","强度",{"key":23,"text":24,"correct":18},"D","刚度","大型储罐的管道与泵或其他有独立基础的设备连接，应在储罐液压（充水）试验合格后安装，或在 储罐液压（充水）试验及基础初阶段沉降后，再进行储罐接口处法兰的连接。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]