[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136376,797,1,"单选题","工业管道安装工程一般施工程序中，试压清洗紧前工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","防腐保温",false,{"key":16,"text":17,"correct":18},"B","仪表安装",true,{"key":20,"text":21,"correct":14},"C","管道预制安装",{"key":23,"text":24,"correct":14},"D","调试及试运行","仪表安装→试压清洗",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]