[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136355,797,1,"单选题","设备基础验收内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","混凝土强度",false,{"key":16,"text":17,"correct":14},"B","位置和尺寸",{"key":19,"text":20,"correct":21},"C","垫铁设置",true,{"key":23,"text":24,"correct":14},"D","预埋地脚螺栓","机械设备安装前，对基础的验收有：设备基础混凝土强度的验收；设备基础位置和尺寸的验收；预埋地脚螺栓的验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]