[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136352,797,1,"单选题","机械设备安装程序中，安装精度调整与检测的紧前工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备固定与灌浆",false,{"key":16,"text":17,"correct":14},"B","垫铁设置",{"key":19,"text":20,"correct":21},"C","吊装就位",true,{"key":23,"text":24,"correct":14},"D","设备装配","机械设备安装的一般程序：开箱检查→基础测量放线→基础检查验收→垫铁设置→吊装就位→安装精度调整与检测→设备固定与灌浆→设备装配→润滑与设备加油→试运转。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]