[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136321":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136321,797,1,"单选题","防雷接地装置施工程序中，引下线敷设的紧后工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接地干线施工",false,{"key":16,"text":17,"correct":14},"B","接地体施工",{"key":19,"text":20,"correct":14},"C","接闪带施工",{"key":22,"text":23,"correct":24},"D","均压环施工",true,"防雷接地装置的施工程序：接地体施工→接地干线施工→引下线敷设→均压环施工→接闪带（接闪杆、接闪网）施工",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]