[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136319,797,1,"单选题","下列关于室内排水管道系统试验的说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","隐蔽的排水管道在隐蔽前必须做灌水试验和通水试验",true,{"key":16,"text":17,"correct":18},"B","安装在室内的雨水管安装后应做灌水试验",false,{"key":20,"text":21,"correct":18},"C","通球球径不小于排水管道管径的2\u002F3",{"key":23,"text":24,"correct":18},"D","通球率必须达到100%","室内排水管道施工技术要求： （1）隐蔽或埋地的排水管道在隐蔽前必须做灌水试验。 （2）安装在室内的雨水管道安装后应做灌水试验。 （3）排水主立管及水平干管管道均应做通球试验，通球球径不小于排水管道管径的2\u002F3, 通球率必须达到100%。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]