[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136217,797,1,"单选题","下列费用中，不属于分部分项工程清单综合单价的是（）.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理费",false,{"key":16,"text":17,"correct":14},"B","材料费差价",{"key":19,"text":20,"correct":21},"C","措施费",true,{"key":23,"text":24,"correct":14},"D","利润","2020版教材P354 \u002F 2019版教材P339 二、工程量清单综合单价的构成：分部分项工程费、措施项目费和其他项目费均采用综合单价计价，综合单价由完成规定计量单位工程量清单项目所需的人工费、材料费、机械使用费、管理费、利润等费用组成，并考虑一定的风险费。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]