[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136214,797,1,"单选题","下列制度中，属于施工内部协调管理组织措施的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立协调会议制度",true,{"key":16,"text":17,"correct":18},"B","费用补偿制度",false,{"key":20,"text":21,"correct":18},"C","质量责任制度",{"key":23,"text":24,"correct":18},"D","教育培训制度","2020版教材P316 \u002F 2019版教材P302 机电工程项目内部协调管理的措施措施是使协调管理取得实效的保证,主要有：1.组织措施：项目部建立协调会议制度,定期组织召开协调会,解决施工中需要协调的问题。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]