[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136210,797,1,"单选题","机电工程项目货物采购不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件编制",true,{"key":16,"text":17,"correct":18},"B","机电设备调试",false,{"key":20,"text":21,"correct":18},"C","机电设备运输",{"key":23,"text":24,"correct":18},"D","机电工程初期维修","2020版教材P244 \u002F 2019版教材P230 货物采购属于有形采购，货物主要包括机电工程项目需要投入的货物，如建筑材料（钢材、水泥、木材等。货物采购还应包括与之有关的服务，如运输、保险、安装、调试、培训、初期维修等。BCD均属于。服务采购属于无形采购，可分为以下阶段的四种类型：1）决策阶段：项目投资前期准备工作的咨询服务。如可行性研究、项目评估。2）设计、招标投标阶段：工程设计和招标文件编制服务。3）施工阶段：项目管理、施工监理等执行性服务。4）其他：技术援助和培训等服务。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]