[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136190,797,1,"单选题","凝汽器组装完毕后,汽侧应进行（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","真空试验",false,{"key":16,"text":17,"correct":14},"B","压力试验",{"key":19,"text":20,"correct":14},"C","气密性试验",{"key":22,"text":23,"correct":24},"D","灌水试验",true,"2020版教材P126 \u002F 2019版教材P116 （2）凝汽器内部设备、部件的安装凝汽器组装完毕后，汽侧应进行灌水试验",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]