[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136178,797,1,"单选题","输配电架空线路施工工序为：线路测量、基础施工、（）等。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","放线架线、杆塔组立、线路试验、导线连接、竣工验收检查",false,{"key":16,"text":17,"correct":14},"B","导线连接、放线架线、杆塔组立、线路试验、竣工验收检查",{"key":19,"text":20,"correct":14},"C","导线连接、线路试验、放线架线、杆塔组立、竣工验收检查",{"key":22,"text":23,"correct":24},"D","杆塔组立、放线架线、导线连接、线路试验、竣工验收检查",true,"2020版教材P84 \u002F 2019版教材P73 架空线路施工架空线路施工的一般程序:施工测量→基础施工→杆塔组立→放线施工→导线连接→竣工验收检查。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]