[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1136156,797,1,"单选题","主控项目是保证安装工程安全和使用功能的重要检验项目，其要求（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必须达到",true,{"key":16,"text":17,"correct":18},"B","应该符合",false,{"key":20,"text":21,"correct":18},"C","不得违反",{"key":23,"text":24,"correct":18},"D","严格把关","2020版教材P474\u002F2019版教材P462 教材原文是：（1）主控项目是指对安全、卫生、环境保护和公众利益，以及对工程质量起决定性作用的检验项目。对于主控项目是要求必须达到的。所以选A。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]