[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1136146,797,1,"单选题","工业分部工程质量验收的结论由（）填写。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设或施工单位",false,{"key":16,"text":17,"correct":18},"B","建设或监理单位",true,{"key":20,"text":21,"correct":14},"C","监理或施工单位",{"key":23,"text":24,"correct":14},"D","设计或监理单位","2020版教材P475\u002F2019版教材P463 分部（子分部）工程质量验收记录的检查评定结论由施工单位填写。验收结论由建设（监理）单位填写。记录表签字人：建设单位项目负责人、建设单位项目技术负责人，总监理工程师；施工单位项目负责人、施工单位项目技术负责人、设计单位项目负责人;年、月、日等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]