[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1136135,797,1,"单选题","主控项目是对工程质量、安全、卫生，环境保护和（），及对工程质量起决定性作用的检验项目。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投产后的运转率",false,{"key":16,"text":17,"correct":14},"B","投产后的产能",{"key":19,"text":20,"correct":14},"C","达产达标周期",{"key":22,"text":23,"correct":24},"D","公众利益",true,"2020版教材P474\u002F2019版教材P462 主控项目是指对安全、卫生、环境保护和公众利益，以及对工程质量起决定性作用的检验项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]