[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136120,797,1,"单选题","分项工程施工完成后由（）组织内部验评。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专业质检员",false,{"key":16,"text":17,"correct":14},"B","项目技术负责人",{"key":19,"text":20,"correct":21},"C","项目专业技术负责人",true,{"key":23,"text":24,"correct":14},"D","施工单位","2020版教材P480\u002F2019版教材P468 2.分项工程验评的工作程序（1）组成分项工程的所有检验批施工完毕后,在施工单位自检的基础上，经项目专业技术负责人组织内部验评合格后，填写“分项工程质量验收记录”,报监理工程师（建设单位项目技术负责人）组织验评签认。 分项工程的是项目专业技术负责人负责组织内部评验；分部工程是项目经理或者项目技术负责人组织内部验评。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]