[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1136118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1136118,797,1,"单选题","在施工前应将单位（子单位）工程划分确定，据此（）和验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织施工",false,{"key":16,"text":17,"correct":14},"B","准备材料",{"key":19,"text":20,"correct":21},"C","收集整理施工技术资料",true,{"key":23,"text":24,"correct":14},"D","规划暂设工程搭建","2020版教材P477\u002F2019版教材P465 在施工前施工单位应会同监理单位（建设单位）根据《建筑工程施工质量验收统一标准》的要求自行商确定分部工程、分项工程和检验批，并据此收集整理施工技术资料和验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]